Nov 27 - Dec 3, 2020
To begin this week off, we install a durable vinyl tile in the back porch area.
Next we hang drywall on the new closet in the back bedroom.
And then we hang new drywall throughout the master bedroom.
Then we paint the back and the front bedrooms.
Next we patch and seal the cracks in the cement floor in the basement.
And then we prep the floors in the main living area and we begin to install the new Laminate flooring.
Finally - with the floors installed in the Kitchen area we install the base cabinets, install the built in microwave and place the dishwasher and range. We also install all the cabinet doors.